PROJECT BACKGROUND
First Creek, an east bank tributary to the South Platte River, originates upstream of Interstate 70 and E470 and generally flows to the northwest. The area upstream of I-70 has been studied several times, but the tributaries to First Creek have not been studied in detail. This study focuses on the tributaries to First Creek upstream of I-70 that have tributary drainage basins greater than 130 acres. The study area encompasses approximately 8.1 square miles and is located within the City of Aurora and unincorporated Arapahoe County. The study is also located within the limits of the Urban Drainage and Flood Control District boundary. The watershed is currently mostly agricultural or open space with some multi-family residential development. Development is anticipated to increase in this area. The change from mostly undeveloped to more urbanized will have a significant effect on the drainage systems within the study area.
PROJECT GOALS
The purpose of this project is to provide HYDROLOGIC ANALYSIS and to develop alternatives and recommendations for STORMWATER INFRASTRUCTURE IMPROVEMENTS that will be needed as development occurs.
KEY PROJECT GOALS
• Clearly define intent of stormwater improvement goals and objectives for future implementation.
• Inform, guide, and provide expectations to manage development effects on stormwater quality, drainageway stabilization, flood risk, etc.
• Integrate proposed improvements with realistic location of future trails, open space, traffic master plans, and development planning.
• Define stream management corridors to provide stormwater conveyance.
• Develop guidance for future vegetation and provide reference for roughness coefficients for maintenance purposes.
PROJECT UPDATES
Click the tabs below for project updates on the First Creek Tributaries Upstream of I-70 Master Drainageway Plan.
SCHEDULE
MEETINGS
REPORTS
TASK
ANTICIPATED DATE
Notice to Proceed
Draft Baseline Hydrology Report
Final Hydrology Report
Draft Alternatives Report
Final Alternatives Report
Arrange and Hold Public Meeting
Draft Conceptual Design Report
Final Design Report
June 18, 2018
December 2018
February 2019
August 2019
November 2019
January 2020
March 2020
May 2020
STATUS
Issued
Complete
Complete
Complete
Complete
Upcoming
Upcoming
Upcoming
MEETING
DATE
MINUTES
Kickoff
Progress Meeting
Progress Meeting
Alternatives Kickoff
Progress Meeting
June 13, 2018
August 30, 2018
January 23, 2019
June 20, 2019
October 24, 2019
PUBLIC MEETING
Tuesday, January 21, 2020, 6-7 PM
Beck Center (8000 Telluride St., Aurora, CO 80011) - Aspen Room
PROJECT ENGINEERS
CONTACTS
PROJECT SPONSORS
Urban Drainage and Flood Control District (UDFCD)
Teresa Patterson, PE, CFM
Project Sponsor
City of Aurora
Sarah Young, PE
Project Sponsor
Craig Perl, PE, CFM
Project Sponsor
Sam Miller, EIT
Project Sponsor
Southeast Metro Stormwater Authority (SEMSWA)
Stacey Thompson, EIT, CFM
Project Sponsor
Arapahoe County
Sue Liu, PE, CFM
Project Sponsor